Three months or three years until delivery

On November 20, 2026, Auterion and Ukrainian company SkyFall announced a joint venture for drone manufacturing in Germany, part of the "Build with Ukraine" initiative. This program aims to facilitate technology transfer and collaboration, revealing challenges in timelines, regulatory processes, and export licensing for defense projects.

11/24/2026  By Redaktion

On November 20, 2026, Auterion and the Ukrainian company SkyFall announced at the 9th German-Ukrainian Economic Forum in Berlin their intention to establish a joint venture for drone manufacturing in Germany. It is the latest of approximately 41 projects under the Ukrainian “Build with Ukraine” program. Anyone investing capital in this market needs a reliable answer to a simple question: How long does it take from the initial memorandum to the arrival of materials in Ukraine? In this issue, SPARTANAT author Jan Hesselbarth calculates the timeline based on publicly documented cases and draws conclusions regarding planning, financing, and distribution.

What “Build with Ukraine” Is

President Zelenskyy publicly announced the program on June 20, 2025. It reverses the direction of previous cooperation: While the Danish model channels foreign capital into Ukrainian factories, “Build with Ukraine” brings Ukrainian technology to manufacturing facilities in partner countries.

The process has four stages:

  • First, a bilateral intergovernmental agreement,
  • then a joint venture or a corporate agreement at the industrial level,
  • then financing by the partner country,
  • and finally, delivery.

In practice, the initial deliveries go to the Ukrainian Armed Forces.

What is missing here is a regulated entry process. The KSE Institute describes the process as follows: A foreign state initiates the process; the Ukrainian Ministry of Defense reviews the request and consults with the General Staff regarding needs; and the decision is based on an administrative act without published criteria. No legal act defines eligible partner states, requirements, or financing mechanisms; each partnership is negotiated individually. For a small-to-medium-sized enterprise, this means there is no application process to follow.

The timeline in documented cases

The fastest case: Octopus in the United Kingdom. On October 25, 2025, the defense ministries in London agreed to the serial production of the Ukrainian Octopus-100 interceptor drone at British facilities. The license agreement followed on November 27, 2025. On December 9, 2025, the British Ministry of Defense announced that production would begin in January 2026. On January 15, 2026, the first four units were successfully tested, with the announcement that they would be delivered to Ukraine shortly. It took about three months from the government agreement to the first hardware; two months from the licensing agreement.

The German case study: Quantum Frontline Industries. In December 2025, Quantum Systems and Frontline Roboticsfounded the joint venture QFI. In February 2026, series production of the Linza 3.0 began in Germany, and the first drone manufactured in Germany was handed over on the sidelines of the Munich Security Conference. On November 20, 2026, the company announced that the initial order for 10,000 Linza systems was nearing completion, that a larger follow-up order from the Ukrainian National Guard had been received, and that production capacity was set to increase fivefold by 2027. It took two months from the establishment of the joint venture to the start of mass production. The groundwork had already been laid: On December 15, 2025, at the 8th Economic Forum, Chancellor Friedrich Merz had presented a ten-point program that called for the production of Ukrainian-developed drones in Germany starting in 2026.

The shortest planned cycle: Norway. On April 14, 2026, Oslo and Kyiv signed a joint declaration on enhanced defense cooperation. The implementation agreement followed on April 27, 2026, and the first Mid-Strike drones manufactured in Norway were scheduled to be delivered to the Ukrainian armed forces as early as the summer of that same year. The timeline called for two to four months. I have not found any independent confirmation that this delivery actually took place. That is part of the picture.

The slow-moving case: Fire Point in Denmark. In June 2025, both sides signed a letter of intent that included $47 million in Danish seed funding, followed by a memorandum of understanding on October 6, 2025. The groundbreaking ceremony in Vojens took place on December 1, 2025. Production has since been postponed to the end of 2027 because construction is taking longer than planned. Costs have risen to over 150 million euros, more than tripling, even though the Danish authorities had previously cleared more than 20 regulatory hurdles. The project, originally planned to take 18 months, will now take around 30.

The Stalled Cases: Lithuania and Poland. The letter of intent with Lithuania is dated August 25, 2025, and the actual agreement was signed on May 13, 2026. Production did not begin by fall 2026. Regarding Poland, the Warsaw Center for Eastern Studies noted in April 2026 that the intergovernmental agreements signed at the turn of the year had not yet been implemented.

The Analysis: Two Speeds, One Bottleneck

These cases reveal two distinct categories. When technology transfer is applied to an existing, certified production line, the cycle takes three to six months until the first hardware is produced. If the project requires a new facility—particularly for energy materials—the cycle takes 24 to 36 months, with a significant risk of delays. These timeframes are my own estimation based on the cases documented above; according to my research, no source exists that reports such figures itself. The KSE Institute explicitly states that no initial delivery date or deadline has been published for any “Build with Ukraine” partnership.

In between lies a third group that does not fit into any statistics. Militarnyi, citing the KSE Institute, estimates that there are approximately 180 international partnerships involving the Ukrainian defense industry—41 of which are under the “Build with Ukraine” initiative—and notes that at least 22 percent of all agreements and memoranda of understanding have stalled. The sentence that sums this up reads: “A memorandum is not a plant.”

One bottleneck explains a large part of the variation: the Ukrainian export license. It involves a multi-agency process involving the Ministry of Defense, the Security Service, the Foreign Intelligence Service, the Ministry of Foreign Affairs, and the State Export Control Agency, and each application is reviewed individually. The company Airlogixtook two years to obtain one; the license granted applies only to a project in Germany—for another partner country, the process starts all over again. Added to this are foreign exchange regulations: A capital contribution to a foreign joint venture requires special approval from the National Bank; in the case of Fire Point, with 20 million euros in share capital, it even requires a separate cabinet decision. A simplification has been in place since July 1, 2026; however, it applies only to countries with a “Drone Deal” agreement, and for “Build with Ukraine”—which lacks this connection—the old procedure remains in effect.

The Octopus project moved quickly because a prerequisite had been met: the Ukrainian Ministry of Defense had established its own Intellectual Property Office in May 2025, and it was only this reform that made the technology transfer to British manufacturing possible. Speed in this context stems from legal work that begins years before the contract is signed.

What this means for your company

First, a planning benchmark. For a project with existing manufacturing facilities, a clarified license, and financing from the partner country, four to eight months from the initial memorandum to the first production run is realistic. Do not base your business case on the best-case scenario of three months, and factor in at least two years for any form of new plant construction.

Second, a key question to consider before any letter of intent. The timeline depends less on your facility than on your Ukrainian partner’s export license for your specific target country. If that license is not in place, any deadline commitment in the memorandum is merely a declaration of intent without substance.

Third, an expectation regarding the customer. The initial deliveries are destined for the Ukrainian Armed Forces and are financed by partner nations. The path to independent defense procurement is a separate, later issue. Auterion’s statement regarding the German perspective remains exactly that: a perspective, without a contract and without specified quantities.

Fourth, a matter of attitude. During my discussions in Kyiv in October 2026, I learned that speed is viewed there as part of performance. Anyone who needs six weeks for internal approval will lose the partner to a faster competitor. Between that pace and a two-year approval process lies the work that no one can do for you.

A memorandum doesn’t move any equipment. It only postpones the moment when you realize something is missing.

The fast-track cases are those in which someone had been working on the legal framework two years in advance.

JAN HESSELBARTH, as co-founder and managing partner of BRAVO SIX ADVISORY GmbH, is responsible for the defense division and brings over 20 years of operational and strategic leadership experience from the German Armed Forces, federal agencies, and the private sector. As a paratrooper officer and Joint Terminal Attack Controller (JTAC), he was responsible for territorial tasks and host nation support at the Hamburg Regional Command following a deployment in Kunduz, Afghanistan. His consulting portfolio includes NATO missions, programs involving up to 1,000 participants, training contributions for more than 5,000 Bundeswehr personnel, and co-authorship of a nationwide study on maritime security for the Federal Ministry of the Interior—a core topic in the context of KRITIS.

BRAVO SIX ADVISORY online

SPARTANAT is the online magazine for Military News, Tactical Life, Gear & Reviews.
Send us your news: [email protected]

similar

We tell you something.
Sign up for the newsletter now!

Get the weekly SPARTANAT newsletter.

Your bonus: the free E-Book from SPARTANAT.

With your registration, you confirm that you have read the privacy policy.